Barn progress pictures

 

 

Starting pictures 10/17/06 (nothing touched)

 

10/18/06 Fence and net removal

 

                                                    10/23/06 Trees and court lights removed        Two dead tree remove above

 

10/29/06 Brick pavers removed for construction

11/14/06

  

11/15/06 Sand removed for construction fence post removed

 

12/11/06 - 1/5/07 Foundation installation

 

 

Basement                                                                 Footings                                                                               

Concrete

 

 

1/15/07   Prefab building delivered

 

1/29/07 - 2/16/07 Building assembled

   

First post installed                                        North to South view (South wall) 1/30/07                           South to North view

1/31/07 pictures

 

2/1/07 pictures

2/2/07 Roof steel complete

    

Fire wall installation 2/12/07

Firewall completed 2/14/07

 

Future bathroom                                      Front Door                                   Future bathroom

2/15/07 pictures

 

 

2/19 & 2/20 pictures

 

Bathroom construction

 

 

 

 

 

2/20/07 pictures

 

2/28/07 pictures

Roof work

 

3/12/07 pictures

Heating duct and radiant tubes installed

 

All doors and garaged doors installed

 

 Radiant heat installed/HVAC system installed

2 - 25 ton A/C and 400,000 BTU of heat units arrived for installation

 

Final inspection 5/1/07

 

 

Open as of 5/1/07